PROJECT
CASE STUDIES
COOK COLLIERY CHPP EXPANSION
-
Project Name: Cook Colliery CHPP Expansion
Client: Caledon Resources
Duration: 9 months
Completed: 2015
Value: $9.2M
Blackwater QLD -
Caledon Resources expanded the existing Cook Colliery Mine CHPP to increase capacity. The project included new civil works for the ROM, CHPP Building, Raw Coal Conveyor & Rejects Conveyor.
-
Bulk and detailed earthworks
Concrete infrastructure
UG service reticulation
Aurizon Rail Culvert works
Drainage works
BYERWEN MINE TLO AND CHPP
-
Project Name: Byerwen Mine TLO & CHPP
Client: Sedgman
Duration: 12 Months
Completed: 2019
Value: $10.2M
Location: Glenden, QLD -
Q Coal developed Byerwen coal mine near Glenden in Central Queensland. C&C were engaged by Sedgman to complete the civil works associated with the construction of the Train Load out (TLO) facility and the Coal Handling Preparation Plant (CHPP).
-
Detailed excavation & backfilling works
Concrete works
Underground Service Reticulation including electrical conduits and raw water
Precast concrete tunnel segment installation and grouting
Drainage structures
Supply and installation of a sewerage treatment plant
IRONBARK COAL MINE – RAW COAL STACKER
-
Project Name: Ironbark Coal Mine – Raw Coal Stacker
Client: Fitzroy Coal Management Pty Ltd
Duration: 5 months
Completed: 2024
Location: Moranbah, QLD -
Fitzroy Coal Management recently built the Ironbark No.1 underground coal mine. As part of this project C&C were engaged to complete the concrete civil works associated with the new Raw Coal Stacker Conveyor structure.
-
Detailed earthworks
UG electrical conduit reticulation
Concrete infrastructure
Cast-Insitu Piling Works
Drain & Sediment capture basins
Liaising with the SMP contractor to ensure scheduled access
Working with the SMP contractor to install and concrete fill steel support columns
PEAK DOWNS MINE LV-MV ROAD & BRIDGE
-
Project Name: Peak Downs Mine LV-MV Road & Bridge
Client: BHP Mitsubishi Alliance
Duration: 8 months
Completed: 2008
Value: $6.3M
Location: Moranbah, QLD -
As part of a business wide safety initiative, Peak Downs Mine built a 2.4km road to separate light and medium transport vehicles from mining heavy vehicles. C&C were engaged to complete the site construction works and project delivery.
-
Road works to QLD Department of Main Roads Standards
Bridge Works to QLD Department of Main Roads Standards
Culverts
Precast Retained Earth walls
Landscaping
Concrete retaining walls
Underground Service Relocations
Rail & Roadway shutdown management to install precast bridge deck units
BMC HV WORKSHOP CIVILS PROJECTS
-
Project Name: BMC HV Workshop Civils Projects
Client: BHP Mitsui Coal (BMC)
Duration: 7 months each
Completed: 2011 & 2023
Value: $13.3M
Location: Moranbah, QLD -
BHP Mitsui Coal (BMC) upgraded mining fleets and facilities at South Walker Creek (SWC) and Poitrel Coal Mines. As part of this expansion C&C were engaged to construct the civil works associated with the new Heavy Vehicle Workshops at each mine site. The project at SWC incorporated the setup of a portable batch plant within the mining lease.
-
Bulk and detailed earthworks
Piling works
Concrete works
Cast-in rails & Angles
HD Bollards
Drainage structures
Underground Service Reticulation
Managing construction activities within an operating MIA
PEAK DOWNS HIGHWAY BRIDGE REPLACEMENT PROJECT
-
Project Name: Peak Downs Highway Bridge Replacement Project
Client: Seymour Whyte Constructions
Duration: 12 months
Completed: 2017
Location: Nebo, QLD -
Seymour Whyte engaged C&C to complete the Form Reinforce & Pour (FRP) component of the four new bridges associated with the Peak Downs Highway Upgrade for the QLD Department of Main Roads. The project consisted of replacing existing timber structures with new concrete bridges comprising of seven, three and two span structures.
-
FRP Bridge Substructure including columns, abutments, and headstocks
FRP Bridge deck kerbs
FRP Relieving slabs
SARAJI MINE BUCKET SHOP
-
Project Name: Saraji Mine Bucket Shop
Client: BHP Mitsubishi Alliance
Duration: 5 months
Completed: 2008
Location: Dysart QLD -
Saraji Mine built a new Bucket Shop Facility in 2008. C&C were engaged by BHP Mitsubishi Alliance to complete site construction works for the project within the existing Mine Industrial Area.
-
Detailed Earthworks
Foundation rock anchors
Concrete works
Drainage
Structural Steel fabrication and installation
Installation of client supplied OH gantry crane
Cladding
Plumbing works including raw water, potable water & hose reels
Underground Service Reticulation
MRC TENIX ALLIANCE WATER INFRASTRUCTURE UPGRADE PROJECT
-
Project Name: MRC Tenix Alliance Water Infrastructure Upgrade Project
Client: Tenix Alliance
Duration: 24 Months
Completed: 2010
Value: $3.6M
Location: Nebo, QLD -
Tenix, Cardno, Parsons Brinckerhoff and Mackay Regional Council (MRC) formed the Tenix Alliance to upgrade water infrastructure assets around Mackay including new Sewerage and Potable Water structures. C&C was engaged by the Tenix Alliance to construct five cast insitu concrete tanks and one Fluoridation Building.
-
Bulk and detailed earthworks
Construction of concrete tanks
Construction of concrete Flowmeter Pit
Design & Construction of Fluoridation Building including commissioning
Installation of associated DICL pipework
HAIL CREEK MINE TSF1
-
Project Name: Hail Creek Mine TSF1
Client: Glencore
Duration: 5 Months
Completed: 2024
Location: Nebo, QLD -
Hail Creek Mine upgraded the tailing disposal from two CHPPs by building an above ground tailings storage facility. The project included the civil and concrete works for a Flocculant Plant, Switchroom and HV switchyard which C&C were engaged to deliver. Project works were completed to schedule within budget constraints and with zero incidents.
-
Bulk earthworks
Detailed Earthworks
Drainage Structures
Trenching for UG services
UG conduit installation
Concrete works
Fencing
Earthing
PEAK DOWNS MINE CHPP MCC REPLACEMENT PROGRAM
-
Project Name: Peak Downs Mine CHPP MCC Replacement Program
Client: BHP Mitsubishi Alliance
Duration: 24 Months
Completed: 2023-2025
Value: $8.5M
Location: Moranbah, QLD -
Peak Downs Mine is in the process of replacing the existing Main Wash Plant Substation, Flotation Substation and ROM Substation. As part of this infrastructure upgrade C&C were engaged by BHP Mitsubishi Alliance to complete the civil works for the MCC5 & MCC8 portions of the project and the Civil and Structural works for the MCC 3 portion. This involved delivery of civil and structural steel construction works within a challenging brownfield environment with significant operational water flows and existing underground services. The projects were completed within budget and schedule constraints with no harm to personnel, equipment or the environment.
-
UG service locations
Relocation of existing services
Asbestos removal
Concrete demolition
Detailed excavation
Concrete works
Drainage structures
HDPE works
Piling
Precast blast wall installation
Fabrication and erection of structural steel
Earthing
Installation of client supplied Switchroom
Management of interactions with CHPP operational activities, operational water flows & UG Services
CARBOROUGH DOWNS MINE OL CONVEYOR
-
Project Name: Carborough Downs Mine Overland Conveyor
Client: Vale
Duration: 9 months
Completed: 2010
Value: $9.4M
Location: Moranbah, QLD -
Vale built an overland conveyor to transport coal from the Carborough Downs Underground Coal Mine to the CHPP with the aim to remove road haulage and reduce GHG emissions. The project included new civil works for the Raw Coal Stacker, Drive Stations, Transfer Stations, Crusher Station, Switch rooms & Raw Coal Conveyor.
-
Detailed earthworks
UG electrical conduit reticulation
Concrete infrastructure – 5,140m3
Largest single concrete pour - 605m3
Drain & Sediment capture basins
Working with the SMP contractor to ensure scheduled access
NORWICH PARK MINE HEAVY VEHICLE WASH FACILITY
-
Project Name: Norwich Park Mine Heavy Vehicle Wash Facility
Client: BHP Mitsubishi Alliance
Duration: 8 months
Completed: 2011
Value: $4.1M
Location: Dysart, QLD -
Norwich Park Mine built a new Heavy Vehicle Wash Facility in 2011. C&C were engaged by BHP Mitsubishi Alliance to complete site construction and commissioning works for the project.
-
Bulk & Detailed Earthworks
Concrete works
Structural Steel fabrication and installation
Plumbing works including pumps, tanks, cannons & recycle system
Electrical components supply and installation including PLC, Switchboards & Lighting
Underground Service Reticulation
JELLINBAH MINE CHPP EXPANSION
-
Project Name: Jellinbah Mine CHPP Expansion
Client: Sedgman
Duration: 5 months
Completed: 2021
Location: Blackwater, QLD -
Jellinbah Mine expanded the capacity of the existing Coal Handling & Processing Plant (CHPP) to increase production. C&C were engaged by Sedgman to construct the concrete foundations associated with the expansion works. The project was completed around an existing operating CHPP.
-
Detailed Earthworks
Concrete works
Drainage structures
Underground electrical service conduits
SHOTCRETE SERVICES CONTRACT
-
Project Name: Shotcrete Services Contract
Client: Anglo American
Duration: 2012 – Present
Completed: Ongoing
Location: Moranbah, QLD -
Since 2012 C&C has been providing UG Shotcreting Services to Anglo American at the Moranbah North and Grosvenor underground coal mines. This contract is serviced by C&C’s fleet of flameproof shotcrete rigs. These innovative machines were developed by C&C to travel around the underground workings and robotically apply Fibre Reinforced Shotcrete (FRS) as a ground support system to the coal strata. As a secondary support system FRS provides a long-term durable solution which saves mine operational costs, reduces dust, reduces gas migration and improves ventilation.
-
Supply of UG labour resources, materials and equipment
Supply & application of FRS for roadways, bulkheads and ground support works to headings, roadways, intersections, cut throughs & roof support
Testing of applied FRS
Aero dusting operations
Supervision of FRS works
Managing interactions with other UG mining activities and Shotcrete application services to ensure safe delivery of services
SARAJI MINE OPTIMISED STRIPPING (SRMOS) WORKSHOP
-
Project Name: Saraji Mine Optimised Stripping (SRMOS) Workshop
Client: Walz Group
Duration: 6 Months
Completed: 2023
Value: $4.2M
Location: Dysart, QLD -
Walz Group engaged C&C to complete the Civil works associated with the BHP Mitsubishi Alliance, Saraji Mine Optimised Stripping Workshop. The project was built as an extension to an existing Heavy Vehicle Workshop within an operating mine industrial area.
-
Bulk Earthworks to build a new select fill and pavement earth pad
Identification and relocation of existing UG water services
Setup of a batch plant for concrete supply close to the mine
Concrete Column Foundations
HV Workshop Concrete Slabs & Aprons
Shotcrete batter protection
Drainage structures
HD bollards
Traffic Management to manage interactions with operational vehicle movements
GOONYELLA MINE 66/11KV SUBSTATION REPLACEMENT PROJECT
-
Project Name: Goonyella Mine 66/11kV Substation Replacement Project
Client: G&S Engineering
Duration: 8 Months
Completed: 2010
Location: Moranbah, QLD -
C&C were engaged by G&S Engineering to complete the Civil Construction works associated with the Goonyella Mine 66/11kV Substation Replacement Project. This project was located within an existing coal mine industrial area and presented significant brownfield challenges.
-
Bulk and detailed earthworks
Drainage structures
Concrete works
Underground Service identification and relocation
Installation of electrical conduits in trenches throughout the industrial area
Earth grids
Precast concrete blast walls
Precast concrete culverts & pits
Fencing
Concrete kerbing
Ballast layer
PEAK DOWNS MINE MIA HV CONCRETE HARDSTAND
-
Project Name: Peak Downs Mine MIA HV Concrete Hardstand
Client: BHP Mitsubishi Alliance
Duration: 5 Months
Completed: 2013
Value: $7.2M
Location: Moranbah, QLD -
Peak Downs Mine upgraded the areas between the HV and MV workshops within the existing Mine Industrial Area to a concrete pavement to reduce maintenance costs following rain fall events. C&C were engaged to complete the site construction works and project delivery.
-
Bulk Earthworks to remove and replace existing subgrade materials
Final trim and blinding of subgrade
Concrete demolition
UG service relocations
Concrete 450mm thick pavement slabs with 75kg/m3 of steel fibres – 2,530m3
HD Bollards
Traffic Management
Managing interactions with operational vehicle movements to facilitate ongoing maintenance works
PEAK DOWNS MINE WASTE MANAGEMENT FACILITY
-
Project Name: Peak Downs Mine Waste Management Facility
Client: BHP Mitsubishi Alliance
Duration: 24 Months
Completed: 2024-2026
Value: $18.5M
Location: Moranbah, QLD -
The existing waste sorting and segregation facility at Peak Downs Mine was replaced with a new facility to service and cater for an increased volume of waste from several sites. As part of this infrastructure upgrade C&C were engaged by BHP Mitsubishi Alliance to complete the bulk and detailed earthworks, building works, fencing, electrical, plumbing and UG service reticulations.
-
Land clearing
Bulk Earthworks and pavements
UG service reticulation for electrical and water
Detailed excavation
Concrete works
Drainage structures
Portal Frame Shed Construction
Compost Array Structures
Electrical infrastructure
Plumbing works
Signage
Operation Buildings
Fencing